-------- Original Message --------
854
NOUS42 KWNO 160302
ADMNFD
SENIOR DUTY METEOROLOGIST NWS ADMINISTRATIVE MESSAGE
NWS NCEP CENTRAL OPERATIONS CAMP SPRINGS MD
1055 PM EDT SUN MAR 15 2009
00Z NAM HAS BEEN DELAYED DUE TO AN EARLIER HUNG JOB ON THE
CCS. INVESTIGATIONS CONTINUE AS TO THE CAUSE. IT APPEARS
THAT THE NAM OUTPUT WILL BE RECD AT THE SAME TIME AS THE GFS
TONIGHT DUE TO THIS DELAY. MORE THAN AN HOUR LATER THAN
NORMAL. SUPPORT STAFF CONTS TO INVESTIGATE THE CAUSE BUT
IT APPEARS THE CCS IS RUNNING FINE CURRENTLY. THE 21Z SREF
WILL ALSO BE DELAYED BY SEVERAL HRS TO DUE THIS EARLIER PROBLEM.
DRA/72387 - UNAVAILABLE ON WEEKENDS
MFL/72202 - 10142
MFR/72597 - 10159
BMX/72230 - MISSING PART A
OAX/72558 - MISSING PART A..IN FOR THE GFS
$$
NEWBY/SDM/NCO/NCEP